The electrician has rerouted all the conduit and is hanging the lights. The Plumber has installed the sinks and toilets in the bathrooms and the carpenter is installing the kitchen cabinets.
With regard to the kitchen, in case you are wondering why we have TWO DRINKING FOUNTAINS, the new ADA rules specify that you have to have two drinking fountains with 6″ of difference in height. R U KIDDING ME!!!! When is this madness ever going to end
The drywall crew are prepping some of the areas that we have marked, and then we should start with the final interior painting sometime next week.
The daylight studio has a coat of bonding epoxy down to increase the adherence of the filler layer and epoxy paints that will be used to paint the studio floor.
Still have to find some light weight room darkening blinds for the natural light studio as it will be used for both natural and studio light duties